How Long Does a Kitchen Renovation Take in Calgary? (Realistic Timelines)
- Mike Bouchard

- Dec 14
- 3 min read

One of the most common questions Calgary homeowners ask before starting a remodel is, "How long does a kitchen renovation take?"
If you’ve seen answers online claiming “3–4 weeks,” that usually leaves out critical factors like permits, inspections, cabinet lead times, and trade coordination.
This guide breaks down realistic kitchen renovation timelines in Calgary so you know exactly what to expect—and how to plan your project without unnecessary stress.
Average Kitchen Renovation Timeline in Calgary
For a full kitchen renovation, most homeowners should expect:
👉 6 to 10 weeks from demolition to completion
This does not include:
Design and planning
Permit approval time
Custom cabinetry manufacturing
Understanding the full timeline upfront helps avoid rushed decisions and mid-project delays.
Kitchen Renovation Timeline Breakdown (Step by Step)
1️⃣ Planning & Design (2–3 Weeks)
Before construction begins, planning sets the foundation for the entire project.
This stage includes:
Layout finalization
Cabinet and material selection
Appliance planning
Permit preparation
Rushing this phase often leads to delays later, especially if material selections aren’t finalized early.
2️⃣ Permits & Approvals (1–4 Weeks)
Many kitchen renovations in Calgary require permits when they involve:
Plumbing changes
Electrical upgrades
Structural wall modifications
Permit timelines vary based on project scope and City of Calgary workloads. Starting the permit process early is one of the best ways to keep your renovation on schedule.
3️⃣ Demolition (3–5 Days)
Once permits are approved and materials are ordered, demolition moves quickly.
This phase typically includes:
Removal of cabinets and countertops
Flooring removal
Wall removal (if applicable)
Unexpected issues such as outdated wiring or plumbing may be discovered during demolition, which can slightly extend timelines.
4️⃣ Rough-In Plumbing & Electrical (1–2 Weeks)
This phase includes:
New plumbing lines for sinks and dishwashers
Electrical upgrades for lighting, appliances, and outlets
Inspection scheduling
Inspection availability is a common source of delays during this stage.
5️⃣ Cabinet Manufacturing & Installation (2–4 Weeks)
Cabinetry is often the longest lead-time item in a kitchen renovation.
Timeline factors include:
Stock vs semi-custom vs custom cabinets
Manufacturer production schedules
Installation complexity
Delays here are usually related to ordering cabinets too late in the process.
6️⃣ Countertops, Flooring & Finishing (1–2 Weeks)
Final stages include:
Countertop templating and installation
Flooring installation
Backsplash and finish work
Appliance installation
Once complete, final inspections are scheduled, and the kitchen is ready for use.
Kitchen Renovation Timeline by Project Type
Small Kitchen Renovation
5–7 weeks
Minimal layout changes
Stock cabinetry
Medium Kitchen Renovation
7–9 weeks
New cabinetry and finishes
Moderate electrical and plumbing updates
Large or Open-Concept Kitchen Renovation
9–12+ weeks
Structural changes
Custom cabinetry
Additional inspections
What Causes Kitchen Renovation Delays?
🔴 Permit Processing
Incomplete applications or scope changes can slow approvals.
🔴 Inspection Scheduling
City inspection availability doesn’t always align perfectly with construction schedules.
🔴 Cabinet & Material Backorders
Custom cabinets and specialty finishes often add weeks if not ordered early.
🔴 Mid-Project Design Changes
Changing layouts or finishes after demolition almost always adds time and cost.
Budget planning—covered in Kitchen Renovation Cost in Calgary—plays a major role in timeline reliability.
How to Keep Your Kitchen Renovation on Schedule
To minimize delays:
Finalize layouts and materials early
Start permits before demolition
Order cabinetry as soon as designs are approved
Avoid mid-project changes
Working with experienced Kitchen Renovations Calgary professionals helps coordinate trades, inspections, and scheduling efficiently.
Frequently Asked Questions
How long does a small kitchen renovation take in Calgary?
Most small kitchen renovations take 5–7 weeks, assuming no major plumbing or structural changes.
Do permits slow down kitchen renovations?
Permits add time upfront but prevent major issues later. Skipping permits often causes bigger delays.
Can a kitchen renovation be done faster?
Only cosmetic updates can be completed in shorter timelines. Full renovations should not be rushed.
Final Thoughts
Kitchen renovations involve more trades, permits, and coordination than most homeowners expect. Understanding realistic timelines helps you plan properly and avoid unnecessary stress.
This article works alongside our Kitchen Renovation Cost Calgary and professional Kitchen Renovations Calgary services to help homeowners prepare with confidence.